Time And Work Questions Placement
Time and Work Questions for Placement Exams - Complete Question Bank
Last Updated: March 2026
Introduction and Importance
Time and Work is a crucial topic in quantitative aptitude that tests your ability to solve problems related to efficiency, productivity, and resource management. This topic forms the foundation for understanding work rates, pipe and cistern problems, and complex collaborative work scenarios.
Why Time and Work Matters:
- High Frequency: Appears in almost all placement and competitive exams
- Real-World Application: Directly applicable to project management scenarios
- Foundation Topic: Essential for Pipes & Cisterns, Speed-Distance-Time
- Logical Thinking: Develops analytical and problem-solving skills
Exams Covering This Topic:
- Placement Exams: TCS, Infosys, Wipro, Accenture, Cognizant, IBM, HCL, Capgemini
- Banking Exams: SBI PO, IBPS PO, IBPS Clerk, RBI exams
- SSC Exams: SSC CGL, SSC CHSL, SSC MTS
- Other Exams: Railway, Insurance, State PSCs, GATE
Complete Formula Sheet and Shortcuts
Basic Formulas:
| Concept | Formula |
|---|---|
| Work | Task to be completed |
| Rate of Work | Work done per unit time |
| Time | Duration to complete work |
| Relationship | Work = Rate × Time |
Fundamental Principles:
- If A can do a work in n days, A's 1 day work = 1/n
- If A's 1 day work = 1/n, A can complete the work in n days
- Combined work = Sum of individual work rates
Working Together Formula:
| Scenario | Formula |
|---|---|
| A and B together | 1/A + 1/B = 1/T (where T = time together) |
| A, B, and C together | 1/A + 1/B + 1/C = 1/T |
| A and B, A leaves | B completes remaining work |
| Efficiency ratio | If A:B = 2:1, A takes half the time of B |
Efficiency-Based Formulas:
| Concept | Formula |
|---|---|
| Efficiency Ratio | If A is twice as efficient as B, A's time:B's time = 1:2 |
| Men-Days Formula | M₁ × D₁ = M₂ × D₂ (for same work) |
| Men-Days-Hours | M₁ × D₁ × H₁ = M₂ × D₂ × H₂ |
| Work variation | M₁D₁H₁/W₁ = M₂D₂H₂/W₂ |
Quick Calculation Shortcuts:
| Situation | Shortcut |
|---|---|
| A does in 10 days, B in 15 days | Together: (10×15)/(10+15) = 6 days |
| A+B in 12 days, A in 20 days | B alone: (12×20)/(20-12) = 30 days |
| Three workers A, B, C | LCM method for combined work |
| Efficiency 3:4:5 | Work ratio in same time = 3:4:5 |
Special Cases:
1. Leaving/Joining Pattern:
- Calculate work done before leaving
- Remaining work = Total - Done
- New person completes remaining
2. Alternate Days:
- Calculate 2-day cycle work
- Divide total work by cycle work
- Handle remainder
3. Wages Distribution:
- Wages ∝ Work done ∝ Efficiency
- If efficiency ratio is 2:3, wages ratio is 2:3
Practice Questions (30 Questions)
Level: Easy (Questions 1-10)
Q1. A can do a piece of work in 10 days and B can do the same work in 15 days. In how many days can they complete the work together?
- (a) 5 days
- (b) 6 days
- (c) 7 days
- (d) 8 days
Difficulty: Easy
<details> <summary>View Solution</summary>Given:
- A's time = 10 days
- B's time = 15 days
Method 1 - LCM Approach: LCM of 10 and 15 = 30 (Total work units)
- A's 1 day work = 30/10 = 3 units
- B's 1 day work = 30/15 = 2 units
- Combined 1 day work = 5 units
- Time together = 30/5 = 6 days
Method 2 - Formula: Time = (A × B)/(A + B) = (10 × 15)/(10 + 15) = 150/25 = 6 days
</details>Q2. A can complete a work in 12 days. B is 60% more efficient than A. How many days will B take to complete the same work?
- (a) 6 days
- (b) 7.5 days
- (c) 8 days
- (d) 9 days
Difficulty: Easy
<details> <summary>View Solution</summary>Given:
- A's time = 12 days
- B's efficiency = 60% more than A
Solution: If A's efficiency = 100%, B's efficiency = 160% Efficiency ratio A:B = 100:160 = 5:8
Time ratio A:B = 8:5 (inverse of efficiency) If A takes 8 units = 12 days B takes 5 units = 12 × 5/8 = 60/8 = 7.5 days
Alternative: B is 1.6 times as efficient, so takes 1/1.6 time B's time = 12/1.6 = 120/16 = 7.5 days
</details>Q3. A and B together can complete a work in 8 days. A alone can do it in 12 days. How many days will B alone take?
- (a) 20 days
- (b) 22 days
- (c) 24 days
- (d) 30 days
Difficulty: Easy
<details> <summary>View Solution</summary>Given:
- A + B = 8 days
- A alone = 12 days
Solution: Let total work = LCM(8,12) = 24 units
- (A+B)'s 1 day work = 24/8 = 3 units
- A's 1 day work = 24/12 = 2 units
- B's 1 day work = 3 - 2 = 1 unit
- B's time = 24/1 = 24 days
Formula: B = (A×T)/(A-T) = (12×8)/(12-8) = 96/4 = 24 days
</details>Q4. If 6 men can do a piece of work in 12 days, how many men are needed to complete the same work in 8 days?
- (a) 8 men
- (b) 9 men
- (c) 10 men
- (d) 12 men
Difficulty: Easy
<details> <summary>View Solution</summary>Given:
- M₁ = 6 men, D₁ = 12 days
- D₂ = 8 days, M₂ = ?
Formula: M₁ × D₁ = M₂ × D₂ 6 × 12 = M₂ × 8 72 = 8M₂ M₂ = 9 men
</details>Q5. A can do a work in 15 days and B can do it in 20 days. If they work together for 4 days, what fraction of work is left?
- (a) 1/3
- (b) 5/12
- (c) 7/15
- (d) 8/15
Difficulty: Easy
<details> <summary>View Solution</summary>Given:
- A = 15 days, B = 20 days
- Work together for 4 days
Solution: LCM of 15 and 20 = 60 units
- A's 1 day = 4 units
- B's 1 day = 3 units
- Combined 1 day = 7 units
- Work in 4 days = 28 units
- Fraction done = 28/60 = 7/15
- Fraction left = 1 - 7/15 = 8/15
Q6. A is twice as good a workman as B. Together they finish the work in 14 days. How many days will A alone take?
- (a) 18 days
- (b) 20 days
- (c) 21 days
- (d) 24 days
Difficulty: Easy
<details> <summary>View Solution</summary>Given:
- A is twice as efficient as B
- A + B = 14 days
Solution: Efficiency ratio A:B = 2:1 If B does 1 unit/day, A does 2 units/day Combined = 3 units/day
Total work = 3 × 14 = 42 units A alone = 42/2 = 21 days
</details>Q7. 12 men complete a work in 18 days. After working for 6 days, 4 more men join. In how many more days will the work be completed?
- (a) 7 days
- (b) 8 days
- (c) 9 days
- (d) 10 days
Difficulty: Easy
<details> <summary>View Solution</summary>Given:
- 12 men × 18 days = Total work
- Work for 6 days with 12 men
- Then 16 men complete remaining
Solution: Total work = 12 × 18 = 216 man-days Work done in 6 days = 12 × 6 = 72 man-days Remaining work = 216 - 72 = 144 man-days
With 16 men: Time = 144/16 = 9 days
</details>Q8. A can do 1/3 of a work in 5 days and B can do 2/5 of the work in 10 days. In how many days can both do the work together?
- (a) 8 days
- (b) 9 days
- (c) 10 days
- (d) 12 days
Difficulty: Easy
<details> <summary>View Solution</summary>Given:
- A does 1/3 work in 5 days
- B does 2/5 work in 10 days
Solution: A's time for full work = 5 × 3 = 15 days B's time for full work = 10 × 5/2 = 25 days
Together: (15×25)/(15+25) = 375/40 = 9.375 days
Or using LCM = 75: A = 5 units/day, B = 3 units/day Combined = 8 units/day Time = 75/8 = 9.375 ≈ 9 days (approx)
</details>Q9. A and B can do a work in 45 days and 40 days respectively. They began the work together but A left after some time and B finishes the remaining work in 23 days. After how many days did A leave?
- (a) 7 days
- (b) 8 days
- (c) 9 days
- (d) 10 days
Difficulty: Easy
<details> <summary>View Solution</summary>Given:
- A = 45 days, B = 40 days
- B works alone for last 23 days
Solution: LCM = 360 units
- A's 1 day = 8 units
- B's 1 day = 9 units
B's work in 23 days = 23 × 9 = 207 units Remaining work = 360 - 207 = 153 units
A and B together = 17 units/day Days worked together = 153/17 = 9 days
</details>Q10. 15 men can complete a work in 10 days. If 10 men are sent to another project, how long will the remaining men take to complete the work?
- (a) 20 days
- (b) 25 days
- (c) 30 days
- (d) 35 days
Difficulty: Easy
<details> <summary>View Solution</summary>Given:
- 15 men × 10 days = Total work
- 10 men leave, so 5 men remain
Solution: Total work = 15 × 10 = 150 man-days Remaining men = 5 Time required = 150/5 = 30 days
</details>Level: Medium (Questions 11-20)
Q11. A and B can complete a work in 12 days and 18 days respectively. They work alternately starting with A. In how many days will the work be completed?
- (a) 14 days
- (b) 14.5 days
- (c) 15 days
- (d) 15.5 days
Difficulty: Medium
<details> <summary>View Solution</summary>Given:
- A = 12 days, B = 18 days
- Work alternately: A, B, A, B...
Solution: LCM = 36 units
- A's 1 day = 3 units
- B's 1 day = 2 units
2-day cycle (A then B) = 5 units Number of full cycles = 36/5 = 7 cycles (35 units) + 1 unit
7 cycles = 14 days, work done = 35 units Remaining 1 unit done by A on day 15 Time = 14 + 1/3 = 14.33 days ≈ 14.5 days
</details>Q12. A can do a piece of work in 30 days, B in 40 days, and C in 60 days. If they work together and get a total wage of ₹1300, how much will A get?
- (a) ₹500
- (b) ₹550
- (c) ₹600
- (d) ₹650
Difficulty: Medium
<details> <summary>View Solution</summary>Given:
- A = 30 days, B = 40 days, C = 60 days
- Total wage = ₹1300
Solution: LCM = 120 units
- A's 1 day = 4 units
- B's 1 day = 3 units
- C's 1 day = 2 units
Efficiency ratio A:B:C = 4:3:2 Total parts = 9
A's share = (4/9) × 1300 = 5200/9 ≈ ₹577.78
Rechecking with cleaner numbers: Ratio 4:3:2, sum = 9 A = 4/9 × 1300 = ₹577.78 (closest to ₹600)
Actually let me recheck: Total = 1300 4:3:2 ratio → A = 4/9 × 1300 = 577.78
</details>Q13. 8 men and 12 women can complete a work in 4 days. If 6 men and 8 women can complete the same work in 6 days, how many days will 4 men and 4 women take?
- (a) 8 days
- (b) 10 days
- (c) 12 days
- (d) 15 days
Difficulty: Medium
<details> <summary>View Solution</summary>Given:
- 8M + 12W = 4 days
- 6M + 8W = 6 days
Solution: Total work = (8M + 12W) × 4 = (6M + 8W) × 6 32M + 48W = 36M + 48W 32M = 36M... Error
Let me redo: (8m + 12w) × 4 = (6m + 8w) × 6 32m + 48w = 36m + 48w 0 = 4m → Error in assumption
Work done by both groups in 1 day: Group 1: 1/4 work Group 2: 1/6 work
Difference: 2M + 4W does (1/4 - 1/6) = 1/12 less So 2M + 4W = 1/12 work per day
From 8M + 12W = 1/4: 4(2M) + 3(4W) = 1/4
Let M = m units/day, W = w units/day 8m + 12w = 1/4 6m + 8w = 1/6
Solving: From eq2: 6m = 1/6 - 8w, m = 1/36 - 4w/3
Substituting: 8(1/36 - 4w/3) + 12w = 1/4 8/36 - 32w/3 + 12w = 1/4 2/9 - 32w/3 + 36w/3 = 1/4 2/9 + 4w/3 = 1/4 4w/3 = 1/4 - 2/9 = (9-8)/36 = 1/36 w = 1/48
m = 1/36 - 4/3 × 1/48 = 1/36 - 1/36 = 0
So women do all work! 4M + 4W = 4 × 1/48 = 1/12 per day Time = 12 days
</details>Q14. A contractor undertook to do a piece of work in 9 days. He employed certain number of men but 6 of them being absent from the very first day, the rest could finish the work in 15 days. How many men were originally employed?
- (a) 12 men
- (b) 15 men
- (c) 18 men
- (d) 20 men
Difficulty: Medium
<details> <summary>View Solution</summary>Given:
- Original time = 9 days
- 6 absent, remaining take 15 days
Solution: Let original men = x Work = x × 9 = (x - 6) × 15 9x = 15x - 90 90 = 6x x = 15 men
</details>Q15. Two pipes A and B can fill a tank in 36 hours and 45 hours respectively. If both pipes are opened simultaneously, how much time will be taken to fill the tank?
- (a) 18 hours
- (b) 20 hours
- (c) 22 hours
- (d) 25 hours
Difficulty: Medium
<details> <summary>View Solution</summary>Given:
- A = 36 hours, B = 45 hours
Solution: LCM = 180 units
- A fills 180/36 = 5 units/hour
- B fills 180/45 = 4 units/hour
- Combined = 9 units/hour
- Time = 180/9 = 20 hours
Formula: (36×45)/(36+45) = 1620/81 = 20 hours
</details>Q16. A pipe can fill a tank in 20 hours. Due to a leak in the bottom, it is filled in 25 hours. If the tank is full, how much time will the leak take to empty it?
- (a) 80 hours
- (b) 90 hours
- (c) 100 hours
- (d) 120 hours
Difficulty: Medium
<details> <summary>View Solution</summary>Given:
- Fill pipe = 20 hours
- With leak = 25 hours
Solution: LCM = 100 units
- Fill rate = 100/20 = 5 units/hour
- Net fill rate = 100/25 = 4 units/hour
- Leak rate = 5 - 4 = 1 unit/hour
- Time to empty = 100/1 = 100 hours
Q17. A and B working together can do a piece of work in 6 days. B and C together can do it in 8 days. A and C together can do it in 12 days. How long will A, B, and C together take to complete the work?
- (a) 4 days
- (b) 5 days
- (c) 16/3 days
- (d) 6 days
Difficulty: Medium
<details> <summary>View Solution</summary>Given:
- A + B = 6 days
- B + C = 8 days
- A + C = 12 days
Solution: Let work = LCM(6,8,12) = 24 units
- A + B = 24/6 = 4 units/day
- B + C = 24/8 = 3 units/day
- A + C = 24/12 = 2 units/day
Adding all three: 2(A + B + C) = 9 A + B + C = 4.5 units/day
Time = 24/4.5 = 24 × 2/9 = 48/9 = 16/3 days
</details>Q18. 20 men can complete a work in 14 days. 20 women can complete the same work in 18 days. 12 men and 15 women started the work and after 8 days, 15 more women joined them. How many days will they now take to complete the remaining work?
- (a) 4 days
- (b) 5 days
- (c) 6 days
- (d) 7 days
Difficulty: Medium
<details> <summary>View Solution</summary>Given:
- 20M = 14 days
- 20W = 18 days
- 12M + 15W work for 8 days, then +15W
Solution: Total work = 20M × 14 = 280M or 20W × 18 = 360W 280M = 360W → M/W = 360/280 = 9/7
Let M = 9 units/day, W = 7 units/day Total work = 20 × 9 × 14 = 2520 units
Work by 12M + 15W in 8 days: = (12×9 + 15×7) × 8 = (108 + 105) × 8 = 213 × 8 = 1704 units
Remaining = 2520 - 1704 = 816 units
New team: 12M + 30W = 108 + 210 = 318 units/day Time = 816/318 = 4 days
</details>Q19. A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B, and C work together, they will complete the work in:
- (a) 8 days
- (b) 10 days
- (c) 12 days
- (d) 15 days
Difficulty: Medium
<details> <summary>View Solution</summary>Given:
- A + B = 12 days
- B + C = 15 days
- C + A = 20 days
Solution: LCM = 60 units
- A + B = 60/12 = 5 units/day
- B + C = 60/15 = 4 units/day
- C + A = 60/20 = 3 units/day
Adding: 2(A + B + C) = 12 A + B + C = 6 units/day
Time = 60/6 = 10 days
</details>Q20. Three pipes A, B, and C can fill a tank in 6 hours. After working together for 2 hours, C is closed and A and B fill the remaining part in 7 hours. How many hours will C alone take to fill the tank?
- (a) 12 hours
- (b) 14 hours
- (c) 16 hours
- (d) 18 hours
Difficulty: Medium
<details> <summary>View Solution</summary>Given:
- A + B + C = 6 hours
- All three work 2 hours, then A + B work 7 hours
Solution: Total work = 6 units (assuming 1 unit/hour combined) Work done in 2 hours by all three = 2 units Remaining = 4 units done by A + B in 7 hours A + B = 4/7 units/hour
A + B + C = 1 unit/hour C = 1 - 4/7 = 3/7 units/hour
Time for C alone = 6/(3/7) = 6 × 7/3 = 14 hours
</details>Level: Hard (Questions 21-30)
Q21. A can do a work in 10 days, B in 15 days. They work for 5 days. The rest of the work is finished by C in 2 days. If they get ₹1500 for the whole work, what is the daily wages of B and C together?
- (a) ₹200
- (b) ₹225
- (c) ₹250
- (d) ₹300
Difficulty: Hard
<details> <summary>View Solution</summary>Given:
- A = 10 days, B = 15 days
- A+B work 5 days, C finishes in 2 days
- Total wage = ₹1500
Solution: LCM = 30 units
- A = 3 units/day
- B = 2 units/day
Work by A+B in 5 days = (3+2) × 5 = 25 units Remaining = 5 units done by C in 2 days C = 2.5 units/day
Efficiency ratio A:B:C = 3:2:2.5 = 6:4:5 Total parts = 15
B's wage = (4/15) × 1500 = ₹400 for total work C's wage = (5/15) × 1500 = ₹500 for total work
B worked 5 days, so daily = 400/5 = ₹80 C worked 2 days, so total = ₹500
Actually, wages are distributed based on work done: A worked 5 days = 15 units, B worked 5 days = 10 units, C worked 2 days = 5 units Ratio = 15:10:5 = 3:2:1 Total 6 parts = ₹1500, 1 part = ₹250
B's share = 2 × 250 = ₹500 (for 5 days), daily = ₹100 C's share = 1 × 250 = ₹250 (for 2 days), daily = ₹125
B + C daily = 100 + 125 = ₹225
</details>Q22. 4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish it in 10 days. In how many days will 10 women working together finish it?
- (a) 30 days
- (b) 35 days
- (c) 40 days
- (d) 45 days
Difficulty: Hard
<details> <summary>View Solution</summary>Given:
- 4M + 6W = 8 days
- 3M + 7W = 10 days
Solution: Total work = (4M + 6W) × 8 = (3M + 7W) × 10 32M + 48W = 30M + 70W 2M = 22W M = 11W
From first equation: 4(11W) + 6W = 50W do work in 8 days Total work = 50W × 8 = 400W units
10 women will take = 400/10 = 40 days
</details>Q23. A, B, and C can do a work in 20, 30, and 60 days respectively. If A is assisted by B and C on every third day, in how many days will the work be completed?
- (a) 12 days
- (b) 15 days
- (c) 18 days
- (d) 20 days
Difficulty: Hard
<details> <summary>View Solution</summary>Given:
- A = 20 days, B = 30 days, C = 60 days
- A works alone for 2 days, then A+B+C on 3rd day
Solution: LCM = 60 units
- A = 3 units/day
- B = 2 units/day
- C = 1 unit/day
Cycle of 3 days:
- Day 1: A = 3
- Day 2: A = 3
- Day 3: A+B+C = 6 Total per 3-day cycle = 12 units
Number of full cycles = 60/12 = 5 cycles Time = 5 × 3 = 15 days
</details>Q24. Two pipes can fill a tank in 20 and 24 minutes respectively and a waste pipe can empty 3 gallons per minute. All three pipes working together can fill the tank in 15 minutes. What is the capacity of the tank?
- (a) 60 gallons
- (b) 100 gallons
- (c) 120 gallons
- (d) 180 gallons
Difficulty: Hard
<details> <summary>View Solution</summary>Given:
- Pipe A = 20 min, Pipe B = 24 min
- Waste pipe = 3 gallons/min
- All three = 15 min
Solution: LCM = 120 units
- A = 6 units/min
- B = 5 units/min
- A+B+Waste = 120/15 = 8 units/min
Waste rate = 6 + 5 - 8 = 3 units/min Given that waste = 3 gallons/min So 1 unit = 1 gallon
Capacity = 120 gallons
</details>Q25. A and B undertake to do a piece of work for ₹600. A alone can do it in 6 days while B alone can do it in 8 days. With the help of C, they finish it in 3 days. Find the share of each.
- (a) A:₹300, B:₹225, C:₹75
- (b) A:₹200, B:₹200, C:₹200
- (c) A:₹250, B:₹250, C:₹100
- (d) A:₹320, B:₹180, C:₹100
Difficulty: Hard
<details> <summary>View Solution</summary>Given:
- A = 6 days, B = 8 days
- A+B+C = 3 days
- Total wage = ₹600
Solution: LCM = 24 units
- A = 4 units/day
- B = 3 units/day
- A+B+C = 24/3 = 8 units/day
- C = 8 - 4 - 3 = 1 unit/day
Efficiency ratio A:B:C = 4:3:1 Total parts = 8
A's share = 4/8 × 600 = ₹300 B's share = 3/8 × 600 = ₹225 C's share = 1/8 × 600 = ₹75
</details>Q26. Two pipes A and B can fill a cistern in 37.5 minutes and 45 minutes respectively. Both pipes are opened. The cistern will be filled in just half an hour, if pipe B is turned off after:
- (a) 5 minutes
- (b) 9 minutes
- (c) 10 minutes
- (d) 15 minutes
Difficulty: Hard
<details> <summary>View Solution</summary>Given:
- A = 37.5 min = 75/2 min
- B = 45 min
- Total time = 30 min
Solution: LCM of 37.5, 45 = 225 units
- A = 225/(75/2) = 6 units/min
- B = 225/45 = 5 units/min
Let B work for x minutes: Work by A in 30 min = 6 × 30 = 180 units Work by B in x min = 5x units
180 + 5x = 225 5x = 45 x = 9 minutes
</details>Q27. A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
- (a) 11 days
- (b) 13 days
- (c) 20 days
- (d) 26 days
Difficulty: Hard
<details> <summary>View Solution</summary>Given:
- A is 30% more efficient than B
- A alone = 23 days
Solution: Efficiency ratio A:B = 130:100 = 13:10 Time ratio A:B = 10:13
If A takes 10 units = 23 days B takes 13 units = 23 × 13/10 = 29.9 days ≈ 299/10 days
Work = LCM approach: Let A's efficiency = 13 units/day B's efficiency = 10 units/day Total work = 13 × 23 = 299 units
Together = 23 units/day Time = 299/23 = 13 days
</details>Q28. 5 men and 2 boys working together can do four times as much work as a man and a boy. Find the ratio of working capacities of a man and a boy.
- (a) 1:2
- (b) 2:1
- (c) 1:3
- (d) 3:1
Difficulty: Hard
<details> <summary>View Solution</summary>Given:
- 5M + 2B = 4 × (M + B)
Solution: 5M + 2B = 4M + 4B 5M - 4M = 4B - 2B M = 2B
Ratio M:B = 2:1
</details>Q29. A tank has a leak which would empty the completely filled tank in 10 hours. If the tank is full of water and a tap is opened which admits 4 liters of water per minute in the tank, the leak takes 15 hours to empty the tank. How many liters of water does the tank hold?
- (a) 2400 liters
- (b) 3600 liters
- (c) 4800 liters
- (d) 7200 liters
Difficulty: Hard
<details> <summary>View Solution</summary>Given:
- Leak alone empties in 10 hours
- With inflow of 4L/min, empties in 15 hours
Solution: Let tank capacity = C liters Leak rate = C/10 per hour
With inflow: Net outflow = C/10 - 4×60 = C/10 - 240 per hour Time to empty = 15 hours
C = 15 × (C/10 - 240) C = 1.5C - 3600 0.5C = 3600 C = 7200 liters
</details>Q30. 12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them. How many days will they take to complete the remaining work?
- (a) 1 day
- (b) 2 days
- (c) 3 days
- (d) 4 days
Difficulty: Hard
<details> <summary>View Solution</summary>Given:
- 12 men = 9 days
- 12 men work 6 days, then 18 men complete
Solution: Total work = 12 × 9 = 108 man-days Work done in 6 days = 12 × 6 = 72 man-days Remaining = 108 - 72 = 36 man-days
With 18 men: Time = 36/18 = 2 days
</details>Companies & Exams That Frequently Ask Time and Work
Top IT Companies:
| Company | Frequency | Difficulty Level |
|---|---|---|
| TCS | Very High | Easy-Medium |
| Infosys | High | Easy-Medium |
| Wipro | High | Medium |
| Accenture | Very High | Medium |
| Cognizant | High | Medium |
| Capgemini | High | Medium-Hard |
| IBM | Medium | Medium |
Banking & Government Exams:
| Exam | Questions | Weightage |
|---|---|---|
| SBI PO | 2-4 | High |
| IBPS PO | 2-3 | High |
| SSC CGL | 2-3 | Medium |
| Railway Exams | 2-4 | Medium |
Product-Based Companies:
- Amazon, Microsoft, Google (focus on efficiency and optimization problems)
- Flipkart (supply chain related scenarios)
Preparation Tips
-
Master the LCM Method: Always assume total work as LCM of individual times for easy calculation.
-
Understand Efficiency Ratios: If A is twice as efficient as B, A takes half the time. Efficiency ∝ 1/Time.
-
Men-Days Formula: M₁D₁ = M₂D₂ is your best friend for workforce problems.
-
Pipes and Cisterns: Inlet = positive work, Outlet/leak = negative work. Net work = sum of all.
-
Wages Distribution: Wages are distributed in the ratio of work done or efficiency, not time worked.
-
Alternate Days Pattern: Calculate work done in complete cycles first, then handle remainder.
-
Chain Rule Practice: When multiple variables change (men, days, hours, work), use M₁D₁H₁/W₁ = M₂D₂H₂/W₂.
Frequently Asked Questions (FAQ)
Q1: What is the most important formula for Time and Work?
A: The fundamental formulas are:
- Work = Rate × Time
- If A can do work in n days, A's 1 day work = 1/n
- Combined work rate = Sum of individual rates
- M₁D₁ = M₂D₂ (for same work)
Q2: How to solve Time and Work problems quickly?
A: Use the LCM method:
- Take LCM of all given days as total work
- Calculate individual daily work rates
- Add/subtract as per the scenario
- Divide total work by combined rate
Q3: What is the difference between Time-Work and Pipes-Cisterns?
A: Conceptually same! In pipes:
- Filling pipe = Worker doing positive work
- Emptying pipe/leak = Worker doing negative work
- Apply same formulas with appropriate signs
Q4: How are wages distributed in Time and Work?
A: Wages are distributed in the ratio of:
- Work done (efficiency × time worked)
- Not just time worked or just efficiency
Q5: How to handle leaving/joining scenarios?
A:
- Calculate work done before the change
- Find remaining work
- Calculate new team's rate
- Divide remaining work by new rate
Master these concepts to ace Time and Work questions in your placement exams!